Project: Paraxylene T-4, J3 Program (Reliance) Equipment: Vapor Recovery Unit Skid Package Client: Zeeco, USA Consultant: Foster Wheeler Energy Ltd
SSIS was entrusted with the detailed engineering, procurement, fabrication, assembly, testing/FAT, supply, and installation support for a comprehensive modular skid system. This skid package includes:
Skid Dimensions: 16 meters x 15 meters
Vessels: 6, including an absorber tower (12 m), carbon beds, 2-phase separator, and hold vessel
Components: Over 150 valves and instruments integrated into the system
Our scope covered everything from instruments and valves to electrical systems, ensuring a complete “plug-and-play” solution with full site support for installation.